31st Street Construction

Post Date:04/21/2017 8:59 AM

Construction on 31st Street is expected to begin Monday, April 24.

The one mile stretch of road between 31st Street and Andrews Highway will be rebuilt with new asphalt. Damaged concrete curb and gutters will also be replaced.

The construction project will consist of three phases:

  • The first phase, Andrews Highway to west of Muskingum, will begin Monday, April 24
  • Second phase: Muskingum to between Roger & Kay
  • Third phase: Between Roger & Kay to Maple

During construction, businesses and homes will remain accessible however, parking on the street will not be allowed.

All three phases of work are expected to be completed by the end of August.

Please contact Public Information Coordinator Andrea Goodson for more information, 432-257-0537.